Overview of Earned Value Management (EVM)


Introduction to Earned Value Management (EVM) provides an overview of the basic concepts and highlights industry trends in its usage over the decades.

Introduction to Earned Value Management (EVM) provides an overview of the basic concepts and highlights industry trends in its usage over the decades.

This paper presents in an easy to understand language an overview of Earned Value Management (EVM). It helps answer these basic questions about the methodology:
- What is EVM?
- What are the key benefits and limitations?
- An extension to the Basic EVM Model
- How to ensure data quality to the EVM system
- How to communicate value created to stakeholders?

Excellent Read!

Download (please login and scroll down)

Download Document: Documents are in common file formats such as Microsoft Word (doc), Powerpoint (ppt), Excel (xls,csv,xlsx), and Adobe pdf.
Download


Related Categories




Related Topics



Related Articles


A Framework For IT Value

In this series, we will discuss IT Value - from its definition to a framework to measure and track it

A New Method for Quantifying IT Value

Applied Information Economics (AIE) is a method for quantifying the value of IT investments. This overview of AIE provides an overview of key IT decision problem, how AIE solves them and how AIE is different from other methods.

A Primer on Earned Value Management (EVM)

 Overview of Earned Value Management (EVM) - what is EVM? Why should we use EVM? How to use EVM?

A Primer on Economic Value Added (EVA) Framework

An excellent guide to Economic Value Added (EVA) - it introduces the framework and provides good guidance on it use. The handbook approaches the topic from a general manager's perspective (not from a quant jock's perspective) so it makes the concept...

A Public Value Framework for Government IT Assessment

Framework to measure the value of IT investments in not for profit organizations such as public or government entities.

A Value-Based Perspective on Business-IT alignment

 Business-IT alignment From a Value-Based Perspective covers the basics of it alignment, value modeling as a tool and provides an overview of VITAL - Value-based IT Alignment.

An Overview of Business IT Alignment

This paper discusses business it alignment - the concept of IT-business strategy alignment proposed by J. Luftman, J. Henderson et al. The concept of strategic alignment and its model are explained in the first section. The second section discusses ...

Cloud Computing Payback

 Cloud computing business case to justify based on return on investment (ROI) and total cost of ownership (TCO)

Earned Value Management (EVM) in a Slide

This slide presents the essence of Earned Value Management (EVM) framework through an example.

Economic Value Added 101

 This paper introduces Economic Value Added (EVA) in simple, easy to understand terms.

Introduction to Earned Value Management (EVM)

A presentation on the Earned Value Management (EVM) methodology. Good read!

Introduction to Earned Value Management Systems (EVMS)

This presentation introduces Earned Value Management Systems (EVMS) in simple, easy to understand terms with practical examples.

Introduction to Economic Value Added (EVA) Framework

 This paper explains in depth the Economic Value Added (EVA) framework, its proper use and compares the framework to other value measurement frameworks.

Introduction to Value Measuring Methodology (VMM)

This presentation provides an introduction to the value measuring methodology (VMM).

Introduction to Value-based IT Alignment (VITAL)

  Value-based IT Alignment (VITAL) overview and discussion on basic underlying principles and components of this it value based framework.

IT Strategy: Introduction to Economic Value Added, EVA

A very good presentation on EVA. Good Read!

IT Value In IT Strategy Maps & IT Balanced Scorecard

 This paper explores the connection between IT value and IT Balanced Scorecard/IT Strategy Maps. It describes patterns of IT value i.e. ways in which IT creates/enables value, connects IT value with cascaded and linked strategic objectives and discu...

IT Value Mapping

Can you say with certainty that your IT is aligned with business? Can you prove it? If improving IT ROI is an imperative for you, read on. This paper will show you how to improve ROI by 10% or more…

IT Value: How to Measure Anything

Enclosed is an introduction to "Applied Information Economics" aka AIE. The author - Douglas Hubbard - provides the value proposition for the value proposition measuring framework! Good Read!

Measuring IT Value Using Intel’s Business Value Index

Want to measure the value of IT? Intel has proposed a solution based upon its "Business Value Index." Attached is an introduction to the methodology.

Measuring IT Value using ITIL

This article discusses measuring IT Value with a service-oriented approach based on ITIL.

Measuring the Value of Intangibles

This presentation discusses the valuation of intangible assets - a great tool to assess the value of information technology and related assets

Part II: A Framework for IT Value

Last week, we lay the foundation for a discussion on IT Value. This week, we look at specific areas where IT creates value.

Part III: A Framework for IT Value

Last week, we focused on revenues. This week, we look at the costs in the IT value equation.

Part IV: A Framework For IT Value

Last week, we discussed the cost dimension of IT Value. This week, we will discuss the time to market dimension.

Part V: A Framework for IT Value

Last week, we discussed the time to market dimension of IT Value. This week, we will discuss the quality dimension.

Part VI: A Framework for IT Value

Last week, we focused on quality and its impact on IT Value. This week, we will take a look at productivity and its impact on IT Value

Part VII: A Framework for IT Value

Last week, we focused on productivity and its impact on IT Value. This week, we will take a look at customer satisfaction and its impact on IT Value

Part VIII: A Framework for IT Value (Risk Dimension)

Last week we discussed customer satisfaction. This week we will look at the risk dimension of IT Value.

Performance-Based Earned Value (PBEVSM)

 This paper describes the Performance-Based Earned Value framework  (PBEVSM) and its benefits.

The CFO Guide to Information Technology Total Cost of Ownership (TCO)

 Guide to Information Technology Total Cost of Ownership (TCO) provides a model to identify, select and fund the best IT projects.

The IT Value Hierarchy

 IT Value Hierarchy provides a framework to assess IT value/roi so a CIO can make better IT project portfolio prioritization decisions.

The Value of IT Investments

An overview to Value Measuring Methodology (VMM).

Total Cost of Ownership (TCO) Case Study - Data Center and Network

 A framework to calculate the total cost of ownership (TCO) of a data center and network room.

Total Cost of Ownership (TCO) for Platform Comparison

 This whitepaper summarizes key factors to consider in a platform cost comparison that evaluates financial costs and benefits of mainframe and distributed platforms.

Total Economic Impact of Virtual Hold’s Virtual Queuing Solutions

This case study uses Forrester's Total Economic Impact (TEI) to evaluate the financial impact of implementing the Virtual Queuing Solutions. The document shows all calculations and assumptions that go into creating this business case using Total Eco...

Understanding the Value of IT

Understanding the IT Value equation is critical to making IT Decisions. This article provides guidance using the education industry.

Using Balanced Scorecard to Build a Value Focused IT Organization

This presentation provides good guidance on using Balanced Scorecard from strategy to execution - driving high performance teams to envision, create and deliver value.

Value Measuring Methodology Guide

A "How to" guide to IT value measurement.


Posted on 02/19/2010 by


Overview of Earned Value Management (EVM) author Webmaster1

Webmaster1

Signup For ThoughtLeader









Subscribe


CIO Index

Our Focus is On Your Agenda

CIO Index is the world's largest professional network for CIOs - of the CIO, for the CIO, by the CIO. 

Over 75,000 CIOs and other IT Executives use CIO Index to Learn, Network and Share.

 

Cioindex, Inc.

  • (+1) 800-309-3550
  • Mon - Fri 9:00am - 5:00 pm
  • 375 North Stephanie St., Ste 1411, Henderson, NV 89014